PRETORIA, 28 October 2026 — South Africa’s Department of Electricity and Energy has postponed the ministerial briefing on the first gas-to-power procurement bid window that was scheduled for this morning. Its notice says a replacement date will be communicated later.


The postponement concerns a media engagement, rather than an announced cancellation of the Gas Independent Power Producer Procurement Programme, or GASIPPPP. Existing records show bids were received in May. The outstanding questions concern selection, financing, fuel supply, grid access and the timetable for electricity delivery.


What changed in South Africa’s gas-to-power programme? The department postponed the 28 October ministerial briefing and said it would announce a new date. The notice does not cancel Bid Window 1. Four bids appear on the official May submission list, but receipt of a bid does not establish a contract, financing or an operating power station.

What was postponed

The department’s original advisory scheduled Minister Kgosientsho Ramokgopa’s briefing for 09:00 on 28 October at GCIS Tshedimosetso House in Pretoria. It was intended to provide an update on the programme and the government’s approach to gas-fired electricity generation.


The subsequent official postponement notice moves that engagement to a later date without specifying a replacement. It does not announce preferred bidders, a revised bid-submission deadline or a construction start.


Green Building Africa’s 28 October report also records the postponement. The operational significance will depend on the substantive procurement update that follows, rather than the change in briefing date alone.


Four submitted projects are on the official list

The official Bid Window 1 list records four bids received on 29 May 2026 under tender DMRE/015/2023/24.


The listed capacities total 2,830 MW. That is an arithmetic sum of submissions, not an award total or electricity already added to the grid. Although the document’s column uses the label “contracted capacity”, its title identifies it as a list of bids received. It should not be read as a contract-award notice.

OIL AND GAS

South Africa Gas-to-Power: Bids, Timetable and Delivery

Kamau Bahati

By

Kamau Bahati

Entertainment Editor

Oct 28, 2026

Oct 28, 2026

6 min read

South Africa postponed its gas-to-power briefing. Explore Bid Window 1, the four submitted projects and the steps between procurement and electricity supply.

Published

Updated:

PRETORIA, 28 October 2026 — South Africa’s Department of Electricity and Energy has postponed the ministerial briefing on the first gas-to-power procurement bid window that was scheduled for this morning. Its notice says a replacement date will be communicated later.


The postponement concerns a media engagement, rather than an announced cancellation of the Gas Independent Power Producer Procurement Programme, or GASIPPPP. Existing records show bids were received in May. The outstanding questions concern selection, financing, fuel supply, grid access and the timetable for electricity delivery.


What changed in South Africa’s gas-to-power programme? The department postponed the 28 October ministerial briefing and said it would announce a new date. The notice does not cancel Bid Window 1. Four bids appear on the official May submission list, but receipt of a bid does not establish a contract, financing or an operating power station.

What was postponed

The department’s original advisory scheduled Minister Kgosientsho Ramokgopa’s briefing for 09:00 on 28 October at GCIS Tshedimosetso House in Pretoria. It was intended to provide an update on the programme and the government’s approach to gas-fired electricity generation.


The subsequent official postponement notice moves that engagement to a later date without specifying a replacement. It does not announce preferred bidders, a revised bid-submission deadline or a construction start.


Green Building Africa’s 28 October report also records the postponement. The operational significance will depend on the substantive procurement update that follows, rather than the change in briefing date alone.


ADVERTISEMENT

Four submitted projects are on the official list

The official Bid Window 1 list records four bids received on 29 May 2026 under tender DMRE/015/2023/24.

Submitted project

Capacity listed in bid record

Fuel technology

Province

Khanyazwe Flexpower

440 MW

Liquefied natural gas

Mpumalanga

Pictor GTP Consortium

990 MW

Liquefied natural gas

KwaZulu-Natal

Kelvin Redevelopment

600 MW

Natural gas

Gauteng

Komatipoort Power

800 MW

Natural gas

Mpumalanga


The listed capacities total 2,830 MW. That is an arithmetic sum of submissions, not an award total or electricity already added to the grid. Although the document’s column uses the label “contracted capacity”, its title identifies it as a list of bids received. It should not be read as a contract-award notice.


The IPP programme overview describes the first window as seeking 2,000 MW of land-based gas-fired generation. The capacity offered through bids and the capacity ultimately selected are different quantities.



The published milestone sequence has several stages

A March 2026 reminder notice confirms the revised 29 May submission date. It set an anticipated preferred-bidder announcement approximately three months afterwards, followed by further commercial and financing milestones.


That estimate is a historical procurement target. Its passage does not itself prove that preferred bidders were appointed. A separate dated decision is needed to establish an award.

ADVERTISEMENT

The notice envisaged commercial close approximately 12 months after preferred-bidder announcement, a financial-close long-stop three months after commercial close, and scheduled commercial operation no later than 36 months after commercial close.


These are relative milestones in the procurement document, rather than confirmed calendar dates for an individual plant.

This distinction is useful for businesses assessing opportunities and communities expecting supply. Selection, signed agreements, financing and commissioning each require their own evidence. A plant cannot be assumed to be generating simply because an earlier bidding deadline has passed.



The proposed 5,000 MW allocation is a separate figure

In its 7 October policy statement, the department described a proposed approach prioritising 5,000 MW of gas-to-power and 4,600 MW of battery storage under the first Section 34 determination associated with IRP 2025.

Those planning figures should not be substituted for the existing 2,000 MW first-window scope, or added to submitted bids as though they were separate completed projects. A reconciled procurement schedule is needed to establish how particular allocations and bid windows relate.


SAnews’ account of the policy announcement describes the intended roles: batteries would store electricity for later use, while gas generation would provide dispatchable supply when renewable output falls or demand rises. These are different functions, even when procured within a coordinated electricity strategy.

Trending Now

Akii-Bua Stadium: Progress, Funding and January Handover

Sports Trends

Kenya–Nigeria Cattle Flight: How Livestock Air Cargo Works

Agriculture

South Africa Gas-to-Power: Bids, Timetable and Delivery

Oil and Gas

Africa Prize 2026: Four Finalists and the Path to Wider Use

Technology and Innovation

Popular Today

Oil and Gas

South Africa Gas-to-Power: Bids, Timetable and Delivery

Social Service

South Africa Water-Services Review: What May Change

Banking and Finance

Pick n Pay Results: Smaller Loss, but Turnaround Is Unfinished

Education

NSFAS 2027 Deadline: Apply by 31 October Through Official Channels

Biography

Kwagga Smith Biography: Age, Real Name and Springboks Career

ADVERTISEMENT

Fuel and financing determine whether a plant can deliver

The department says fuel availability, delivered gas prices, port and pipeline infrastructure, grid connections and commissioning schedules must be assessed together. A generation allocation alone does not secure those components.


For each project, the practical questions are who supplies the fuel, what infrastructure is required, how supply interruptions are managed and what price risks fall on the generator or electricity buyer. Financing also depends on the eventual contractual obligations and the project’s expected operating pattern.


No single total investment cost, financing package or electricity tariff for the four submitted projects is established by the bid-receipt list. Nor does it establish jobs already created. Those figures require project-specific disclosures.


Households and industrial customers will judge delivery through dependable electricity and its cost. The next useful announcement is therefore a documented procurement decision with conditions, followed by clear commercial, financing and construction milestones. Rescheduling the briefing can restore an opportunity to explain that sequence; it does not replace the sequence itself.



ADVERTISEMENT

Related Articles

Image-place-holder_edited.png

Oil and Gas

South Africa Gas-to-Power: Bids, Timetable and Delivery

A postponed briefing leaves the next announcement pending as fuel, funding and grid questions remain.

Image-place-holder_edited.png

Social Service

South Africa Water-Services Review: What May Change

Public comments close on 30 October as South Africa reviews water and sanitation delivery.

Image-place-holder_edited.png

Banking and Finance

Pick n Pay Results: Smaller Loss, but Turnaround Is Unfinished

Boxer and better supermarket trading lift results, while the core business still needs to recover.

Image-place-holder_edited.png

Education

NSFAS 2027 Deadline: Apply by 31 October Through Official Channels

Check the application steps, required forms and fraud warnings before the funding window closes.

Tags

Southern Africa News

Breaking News

South Africa

bottom of page